Commencement of Workover, Completion, and Matrix Acidizing Operations on Gas wells of Phase 14 of South Pars Fields
Workover, completion, and acidizing operations on 22 wells at Platforms A and C of Phase 14 of the South Pars Gas Field have been initiated by Global Petro Tech Kish Company, with the aim of maintaining and increasing gas production capacity.
Workover, completion, and
acidizing operations on 22
wells at Platforms A and C of Phase 14 of the South Pars Gas Field
have been initiated by Global
Petro Tech Kish Company, with the aim of maintaining and
increasing gas production capacity.
The
project is planned to be executed over a two-year period in two main sections: 11 wells will undergo
acidizing operations, while the other 11 wells will undergo
the complete workover, completion, and acidizing process. The
primary objective of these operations is to increase the gas production rate
and enhance sustainable production in Phase 14.
Acidizing,
as one of the stimulation methods used to improve gas production rate plays a
key role in this project. According to forecasts, upon completion of the
project, gas production capacity from Platforms A and C of Phase 14 increase
by 100% playing an important role in ensuring the country’s stable gas supply,
particularly during the cold season.
It
is worth noting that South
Pars Phase 14 is considered one of the most important
development phases of the South Pars Gas Field. The implementation of this
project, relying on domestic capabilities, represents an important step toward
realizing the country’s policies of a resilient
economy and self-sufficiency in the energy industry.